Spoil Calculator

Bank to loose (or loose back to bank) with your bulking factor, plus truck loads.

Example inputs are editable. Use your project values. Enter 0 where no optional allowance is intended; blank fields pause the calculation.

Your inputs

Your results

Bank volume
150 m³
Loose spoil
187.5 m³
Truck loads (by volume)
21

These free results do not automatically save or sync to a Fieldlink job.

How it works

  • Loose = bank × (1 + bulking %)
  • Bank = loose ÷ (1 + bulking %)
  • Loads = loose ÷ truck capacity (rounded up)

Worked example

150 m³ bank @ 25 % bulking = 187.5 m³ loose = 21 loads @ 9 m³

Assumptions and practical notes

Bank = in-ground, loose = on the truck, compacted = placed fill. Check payload as well as bin volume for heavy material.