Excavation Volume Calculator

Calculate excavation volume, loose spoil and estimated truck loads for a rectangular dig-out.

Example inputs are editable. Use your project values. Enter 0 where no optional allowance is intended; blank fields pause the calculation.

Your inputs

Your results

Bank volume
188.16 m³
Loose volume (spoil)
235.2 m³
Estimated truck loads
27

These free results do not automatically save or sync to a Fieldlink job.

How it works

  • Bank volume = L × W × average depth
  • Loose volume = bank × (1 + bulking %)
  • Truck loads = loose ÷ truck capacity (rounded up)
  • Tonnes = bank volume × density

Worked example

42 m × 3.2 m × 1.4 m = 188.16 m³ bank × 1.25 bulking = 235.2 m³ loose ÷ 9 m³ trucks = 27 loads

Assumptions and practical notes

Bulking varies by material — clays commonly ~25–30 %, granular less. Batters and over-dig aren't included; allow for them in your average depth/width.

Working on the full job?

Review dig-out and cartage quantities as part of the full estimate.

Explore earthworks estimating