Labour Charge-Out Calculator

An indicative check on what an hour of labour needs to be charged at once on-costs, overheads and non-productive time are covered.

Example inputs are editable. Use your project values. Enter 0 where no optional allowance is intended; blank fields pause the calculation.

Your inputs

Your results

True employment cost
$41.9/hr
Break-even per productive hour
$61.29/hr
Target charge-out
$72.11/hr
Annual chargeable hours (approx)
1,768 hrs
Annual recoverable revenue at target
$127,492

These free results do not automatically save or sync to a Fieldlink job.

How it works

  • Employment cost = wage × (1 + on-costs %) + allowances + vehicle/tools
  • Break-even = employment cost ÷ productive % + overhead
  • Charge-out = break-even ÷ (1 − margin %)
  • Annual chargeable hours ≈ 2080 × productive %

Worked example

$32 wage + 20 % on-costs + $3.50 extras = $41.90/hr ÷ 85 % productive + $12 overhead = $61.29 break-even ÷ (1 − 15 %) = $72.11/hr target

Assumptions and practical notes

Use your actual costs on a consistent GST basis. On-cost and productive-time defaults are examples, not prescribed employer contributions. Annual figures assume 2,080 paid hours before the productive-time factor; adjust your own annual model where this does not fit.