How to Prepare a Construction Variation

Share

Quick answer

A defensible variation has four parts: the instruction (who directed the change and when), the scope (exactly what's extra or different), the cost build-up (labour, plant, materials, subcontractors and other, each with markup), and the approval trail. Price it and submit it before the work disappears into the job.

Skip the maths — free toolFree Variation Template

1. Anchor it to an instruction

Every variation starts with why. Record the source — engineer's instruction, client email, site meeting minute, latent condition — with a reference and date. 'The client told us on site' is worth very little six months later; an EI number or email is worth everything. If the contract requires notice within a set time, that clock is already running.

2. Describe the change, not the argument

Write the scope factually: what was in the contract, what changed, and what the extra or different work is. Keep it to what a reviewer can verify — 'additional 24 m of 300 mm SW line including excavation in rock and reinstatement' beats a paragraph of justification. Attach the marked-up drawing or photos.

3. Build the cost by category

Formulas

Direct cost = labour + plant + materials + subcontractors + other

Markup applied per category (own work vs subcontract often differ)

Variation value = direct cost + markup (+ GST where applicable)

Worked example

Labour: 2 crew × 2 days = $2,720 @ 15 % = $3,128

Plant: digger + truck 2 days = $3,400 @ 15 % = $3,910

Materials: pipe & bedding = $1,850 @ 15 % = $2,127.50

Subcontract: reinstatement = $1,200 @ 10 % = $1,320

Variation total (excl. GST) = $10,485.50

4. Track it to approval

A priced variation that never gets approved is a donation. Track each one through pending → submitted → approved, and don't let approved variations get missed off the next progress claim — they're part of the revised contract value.

Check your contract's variation and notice clauses; some contracts price directed variations from schedule rates and others from actual cost, and the difference matters when you build the claim.

  • Number variations sequentially (VO-001, VO-002…) and reference them in claims
  • Keep daily records for time-and-materials variations — dockets win arguments
  • Update the revised contract value as approvals land