Fieldlink NZ
FIELDLINKNZ
Start 30-day free trial
Civil Hub guide

How to Calculate Pipe Fall & Grade

Share

Quick answer

Pipe fall is the difference between the upstream and downstream invert levels. Grade % = fall ÷ length × 100. The 1:X gradient is length ÷ fall — so 300 mm of fall over 30 m is 1 %, or 1:100.

Skip the maths — free toolPipe Grade Calculator

The three ways drainlayers express grade

The same slope gets written three ways on drawings and consent conditions, and you need to move between them without thinking:

  • Gradient 1:X — one unit of fall per X units of run (1:100 = 10 mm per metre)
  • Grade % — fall as a percentage of length (1:100 = 1 %)
  • mm per metre — literal fall per metre of pipe (1:100 = 10 mm/m)

The calculations

Formulas

Fall = upstream IL − downstream IL

Grade % = fall ÷ length × 100

Gradient 1:X where X = length ÷ fall

Required fall for a target gradient = length ÷ X

End invert = start invert − required fall

Worked example

Worked example

Run: 42.5 m of 150 mm pipe

Upstream IL 12.840, downstream IL 12.245

Fall = 12.840 − 12.245 = 0.595 m (595 mm)

Grade = 0.595 ÷ 42.5 × 100 = 1.4 %

Gradient = 42.5 ÷ 0.595 = 1:71.4

Setting a pipe to a required gradient

Working the other way is just as common: you know the start invert and the minimum gradient, and you need the downstream invert. Required fall = length ÷ X. For 30 m at 1:100 that's 30 ÷ 100 = 0.3 m, so the end invert is 300 mm below the start.

Minimum gradients come from the drainage standard and the network operator's requirements for the pipe size and use — check the approved drawings and local code of practice rather than assuming. Laying flatter than consented is a failed inspection and a re-lay.

Pricing the whole drainage job? Fieldlink takes pipe runs from takeoff to estimate with your own laying rates.

See Drainage Estimating